Bridge girder frame work process and precautions (part 1)
2015-01-06 16:28
Bridge girder frame work process and precautions (part 1)
Erecting Machine usually set up the beams by the steps of feeding precast, tied, lifting, and dropping down these four processes.
(1) Feeding beam
① before entering the bridge beams machine, you should first check whether the impact on the whole obstacle beams ahead and check whether the beam capstone quince high, affecting feed beams.
② should be checked before feeding back end of the bridge support beam to prevent feeding beam bridge back end when excessive amount of subsidence.
③ Yun Liang seat should someone care to prevent and erecting machine collide. Beam carrier should be someone responsible for starting or stopping.
④transporting beams disabled in the backend or scaffold board to stand forward with beams, roof beams to prevent falling objects wounding.
⑤ When erecting machine feed beam, girder vehicle should slowly push. Beams advance should send someone to observe, to prevent the beam or girder vehicle collided with the bridge machine.
(2) Bundle beam
① should be well tied girder iron tile, iron tile to be positive on both sides, so that the rope in the middle of the iron tile, and check whether the child knotted rope, twisting strength relative to the rod pressure or care, etc.
Distance
② two beams hanging pitch endpoint should be equal, so as not to cause uniform discontinuity hoist overload.
③ extremely heavy rope tied beam should generally be kept vertical, not Xiegua. Banned from the vertical or horizontal position strong push iron pole rope hanging jin, avoid violent swing when lifted, or cause a sudden slide rope, cut the wire, crushing beam.
Erecting Machine usually set up the beams by the steps of feeding precast, tied, lifting, and dropping down these four processes.
(1) Feeding beam
① before entering the bridge beams machine, you should first check whether the impact on the whole obstacle beams ahead and check whether the beam capstone quince high, affecting feed beams.
② should be checked before feeding back end of the bridge support beam to prevent feeding beam bridge back end when excessive amount of subsidence.
③ Yun Liang seat should someone care to prevent and erecting machine collide. Beam carrier should be someone responsible for starting or stopping.
④transporting beams disabled in the backend or scaffold board to stand forward with beams, roof beams to prevent falling objects wounding.
⑤ When erecting machine feed beam, girder vehicle should slowly push. Beams advance should send someone to observe, to prevent the beam or girder vehicle collided with the bridge machine.
(2) Bundle beam
① should be well tied girder iron tile, iron tile to be positive on both sides, so that the rope in the middle of the iron tile, and check whether the child knotted rope, twisting strength relative to the rod pressure or care, etc.
Distance
② two beams hanging pitch endpoint should be equal, so as not to cause uniform discontinuity hoist overload.
③ extremely heavy rope tied beam should generally be kept vertical, not Xiegua. Banned from the vertical or horizontal position strong push iron pole rope hanging jin, avoid violent swing when lifted, or cause a sudden slide rope, cut the wire, crushing beam.